Honolulu Rail Truth Map · Active Pilot

HART Total Project Cost

As of December 2025
Source: HART Monthly Progress Report
Updated monthly

Four questions. Four answers. One structured, auditable record.

1

Where are we financially?

Total Project Cost $10.08B Reported
Incurred to Date $6.60B Reported
Remaining to Complete $3.48B Derived
74.23% spent 25.77% remaining
Source: HART Monthly Progress Report, Dec 2025 · Page 35
2

Where is cost heading?

Current Forecast $10.08B
Stable since 2022 Recovery Plan
2012 $5.1B Original estimate
2017 $8.2B Scope revision
2022 $10.08B Recovery Plan baseline
Source: HART Recovery Plan Reports, 2012–2025
3

Do we have the money?

Total Funding Authorized $10.08B Reported
Forecast Total Cost $10.08B
Funding Position Balanced
Funding includes FTA grants, GET surcharge, and City contributions
Source: HART Financial Plan Summary, Q4 2025
4

When will it be done?

East Kapolei to Aloha Stadium Completed June 2023
City Center Segment Forecast: 2031 Under construction
Revenue Service Date 2031 Reported
Source: HART Project Schedule Baseline, Rev. 8

The Honolulu Rail project is 85% spent, with a $125M funding cushion and a stable forecast targeting 2031 completion.

December 2025 Monthly Progress Report
HART Official Document · Page 35, Table: 2022 Recovery Plan Budget Estimate at Completion
Retrieved: February 2026 · Board agenda item archived
Extraction & Citation Sheet
Google Sheet · Extraction tab with page/section references for each metric
Source of truth for displayed numbers and their citations
Date
Old → New
Delta
Reason
Feb 2026
Nov → Dec 2025 MPR
+$66.95M incurred
v0.2 update: December 2025 Monthly Progress Report. Incurred-to-date increased to $6.601B (74.23% of EAC base cost). Source: Board agenda item, p.4 Summary and p.35 Total Project Cost table.
Jan 2026
Oct → Nov 2025 MPR
+$51.26M incurred
v0.1 update: November 2025 MPR (high-res). Incurred-to-date reached $6.534B (73.48% of EAC base cost).
Dec 2025
Initial entry
v0.0 pilot launch. Baseline established from October 2025 Monthly Progress Report.
Incurred to Date (Life-to-Date)
Cumulative incurred costs through the reporting cutoff date, per HART's Monthly Progress Report definition. Note: The MPR may specify inclusions/exclusions (e.g., third-party reimbursement costs). We adopt the definition as stated in the cited source.
Remaining to Complete (Derived)
A derived value calculated from the same primary-source table: Current Forecast "Total Project Cost" − "Incurred to Date." We label this as derived unless the primary source explicitly reports a "cost to complete" line item.

Traceable, Verifiable, Accountable

Each number on this page links to a specific page and section in an official HART document. Click the receipt links above to verify the source data yourself. Any change produces a visible, auditable log entry.